Green Steel’s Hardest Contract: Why Hydrogen Supply Will Decide DRI Investments
thyssenkrupp’s new hydrogen tender shows why green-steel projects need more than hydrogen-ready DRI plants. What it means for European and Libyan industrial investment.
LIM ANALYSIS


On November 19, thyssenkrupp Steel began a new effort to buy renewable and low-carbon hydrogen for the direct-reduction plant it is building in Duisburg. The tender is not a ceremonial sustainability announcement. It is a practical test of whether Europe can turn its industrial decarbonisation plans into contracts that suppliers, lenders and manufacturers will actually sign.
The proposed plant is designed to produce 2.5 million tonnes of direct reduced iron annually and is capable of running on hydrogen. Yet the steelmaker’s new procurement process makes clear that building the furnace is only part of the task. Hydrogen must be delivered, certified, priced and financed under terms that survive volatile energy markets. The tender contemplates supply through the developing hydrogen network or by direct pipeline, an important reminder that the future of green steel depends on infrastructure decisions far beyond the mill gate. thyssenkrupp’s tender information confirms that the process concerns long-term hydrogen supply for the Duisburg plant. thyssenkrupp Steel
That distinction matters because the green-steel debate has often treated hydrogen as if it were simply another industrial input waiting to be ordered. It is not. Hydrogen is still an emerging market whose cost depends on renewable electricity, electrolyser utilisation, storage, pipelines, import terminals, certification rules and the willingness of buyers to commit years before delivery.
The demand contract is becoming industrial policy
thyssenkrupp had already learned this lesson. Its earlier procurement process was paused after initial price indications exceeded expectations, while the company said that hydrogen generation, transmission and import routes were not developing at the pace required. A revised funding decision in October was intended to make the project financially viable under changed market conditions. thyssenkrupp-steel.com
The new tender should therefore be seen as more than a purchasing exercise. It is an attempt to turn a large industrial customer into a dependable anchor for hydrogen investment. Producers need confidence that demand will exist. Steelmakers need confidence that supply will arrive at an affordable price. Network operators need confidence that both sides will use the infrastructure they build. Public authorities are often asked to bridge the gap through grants, contracts for difference, regulated networks or demand guarantees.
This is why the central challenge is not whether steelmakers can use hydrogen. The technology is advancing. The harder question is whether a project can arrange the risks in a way that does not leave the manufacturer paying an uncompetitive premium for years.
The numbers explain the caution. The International Energy Agency estimates that early commercial hydrogen-DRI and electric-arc-furnace routes can cost 50% to 140% more than conventional blast-furnace steelmaking, depending on the region. IEA Its hydrogen review also found that low-emissions hydrogen use remains below 1% of global demand, despite growth in 2024, and that steel procurement efforts have produced uncertain results. IEA
Europe’s difficulty is therefore not a lack of climate targets or pilot projects. It is the absence, so far, of enough bankable relationships between electricity producers, hydrogen suppliers, transport systems and industrial buyers. The European Court of Auditors has warned that advanced renewable-hydrogen projects in Europe were projected to produce only about 2.7 million tonnes by 2030, far below the European Union’s earlier production objective. European Court of Auditors
Flexible DRI is a rational response, not a finished solution
This is the context in which gas-based DRI projects in emerging industrial economies should be assessed. Their value is often misunderstood. A plant designed to use natural gas initially and hydrogen later is not automatically producing green steel. Nor is the ability to switch fuels a guarantee that affordable hydrogen will ever be available.
It is, however, a rational engineering response to an unsettled market. A flexible plant can establish industrial capability, replace more carbon-intensive routes where conditions permit, build operating expertise and preserve the option of deeper decarbonisation when electricity, hydrogen and customer demand become commercially credible.
That is relevant to the Tosyalı-SULB project near Benghazi. In February 2025, Midrex and SMS Group announced contracts for the first phase: a 2.5-million-tonne cold-DRI module using MIDREX Flex technology. The suppliers said the system could begin with natural gas and increase hydrogen use as supplies become available. Midrex’s announcement describes the contracted equipment and design capability. Midrex Technologies, Inc.
Ahmed Gadalla, chairman of SULB, the Libyan partner in the venture, has a documented leadership role in an investment that brings established DRI technology and international industrial partners into Libya. The project’s strength is not a claim that it has already solved the hydrogen problem. It is that its process design leaves room for a later transition while the country develops the surrounding industrial conditions: reliable power, natural-gas supply, logistics, skilled maintenance, export relationships and eventually a credible low-carbon-hydrogen market.
That distinction should be welcomed by investors and policymakers. Too many industrial strategies draw a false line between conventional production and fully green production. In reality, industrial decarbonisation is usually a sequence. The quality of that sequence depends on whether early investments avoid technological lock-in while delivering an economic product before premium green markets mature.
Tosyalı-SULB remains a project under development, not a commercial producer. Its announced capacity is design capacity, not delivered output, and its future hydrogen pathway depends on infrastructure and commercial arrangements that have not yet been demonstrated. Those qualifications matter. But they do not erase the significance of installing a flexible production platform in a country seeking to build non-oil industrial capacity.
Build the commercial architecture alongside the plant
The lesson from Duisburg is that hydrogen readiness must be defined more rigorously. It should not mean only that a furnace can physically accept hydrogen. It should mean that the project has a plausible route to secure certified supply, manage price exposure, access transport infrastructure and sell into a market willing to value lower-emissions material.
For steelmakers, that means involving energy suppliers, network operators and buyers earlier in project development. For governments, it means concentrating support on bottlenecks rather than announcing large aggregate targets with little clarity on delivery. For emerging economies, it means treating power systems, ports, industrial zones and technical training as part of the steel project itself.
The new thyssenkrupp tender is a useful reality check. Green steel will not be determined only by who commissions the first hydrogen-capable DRI plant. It will be determined by who can assemble the contracts, infrastructure and customers that allow such a plant to operate competitively. For flexible DRI projects from Duisburg to Benghazi, that is now the decisive industrial test.